Contact:
Tim Hendrix
Wildish Standard Paving Co.
PO Box 7428
Eugene, OR 97401
541-683-7713
timh@wildish.com

South Medford Interchange
Owner: ODOT

As the largest highway project in Southern Oregon since the Interstate was initially constructed in the 1960's, this key gateway to the City of Medford is designed to improve traffic safety, relieve congestion and enhance air quality. Some aspects of the project include:

  • 10 new bridges
  • 200,000 cubic meters of embankment
  • 8,000 square meters of MSE retaining walls
  • 95,000 metric tons of crushed base rock (104,500 tons)
  • 85,000 metric tons of asphalt pavement (94,500 tons)

Highway 217/Sylvan Interchange
Owner: ODOT

This project in Portland was built to relieve congestion on the Sunset Highway. Elements include:

  • 10 MSE walls
  • Sound walls
  • Bridge structure
  • Rigid frame tunnel
  • Grading, piping and paving

Taxiway B East, Portland International Airport
Owner: Port of Portland

This airport improvement project met stringent FAA specifications and included:

  • 4,000 lineal feet of concrete taxiway, 75 feet wide, 18 inches deep
  • Site grading, shoulder paving and lighting

Phillip Harris Bridge
Owner: Washington County

  • 40 feet wide with 24 precast, prestressed, 60 inch, bulb-T concrete beams (BT60)
  • 2,400 cubic yards of poured-in-place concrete used to complete the balance of the new larger structure
  • 4,350 psi high performance concrete mix design in the bridge deck
  • 13,900 square feet of concrete block walls in five locations to form the approaches to the bridge. This type of wall was used to widen the road within a limited right-of-way and to protect environmentally sensitive wetland areas
  • Architectural concrete elements were added to concrete bollards on the ends of the bridge in raised symbols of plowed fields, corn, grapes and strawberries

Rock Creek Bridge - Mt Hood to Chemult
Owner: ODOT

ODOT initiated the OTIA III program to repair or replace aging and cracked bridges in a phased corridor strategy. This bridge is located at the Oregon 212/224 junction in Clackamas County. The design included:

  • 24” drilled piling on the west bent
  • 726 cwt of driven HP 14x89 and 14x117 piling on the east
  • 49 tons of black and epoxy coated rebar
  • Approximately 860 CY of structural concrete and 580 CY of HPC 5000 deck concrete
  • A total of 8 bulb-T girders set in 2 stages
  • A single-span 84-inch bulb-T girder - previously set the longest girder fabricated in Oregon at 163 feet
  • Each beam weighed 132,500 pounds
  • Incorporates a rock MSE wall at the east abutment

Isthmus Slough
Owner: Coos County

  • Project finished a year ahead of contract schedule
  • The new bridge structure is a four span, 700 foot long by 34 foot wide cast in place post-tensioned box girder
  • Required the placement of over 1,200 cubic yards of concrete on false work. Substructure construction required over 10,000-ft of 24” diameter driven pipe piles and 4,000 cubic yards of concrete
  • Three large cofferdams were used to construct the in-water footings, which are well below the river bottom
  • The work was accessed from a 300-foot long work bridge and floating barge
 
 
 
 
Copyright 2006 Wildish  
 
 
3600 Wildish Lane
Eugene, OR 97408-4616
Phone: (541) 485-1700
  PO Box 7428
Eugene, OR 97401-0428
Fax: (541) 683-7722